An application has an SLA which states that the application must be restored within 12 hours, with no more than 10 minutes of data loss. This means the application has an RTO of 12 hours and an RPO of 10 minutes.
If the design specifies an RTO of 3 hours and an RPO of 2 hours, and the system crashes at 8:00pm., the application has to be back online _______________.
You are a VMware designer working on virtualizing a business application. The SLA specifies that the RTO requirement is 4 hours, and the RPO requirement is 9 hours. After months of successful use, the system crashes at 1 p.m. To meet the project SLA, which of the following is true?
You are a VMware architect working at a company where a business application is being rolled out. Based on conversations with the business, you establish that the RTO requirement is 2 hours, and the RPO requirement is 3 hours. Consider a situation in which the VMware platform is out of service following multiple hardware issues. The application dropped from service at 2 p.m. To meet the application business SLA, which of the following is true?
Which of the following diagrams which may be included in project documentation shows a system's components and how they could affect/depend on each other?