1.
A POWER7 server has 2 VIO Server partitions which provide all disk and networking resources to 4 client IBM i LPARs. How many physical Ethernet adapters will be required to provide each client IBM i LPAR networking support, including failover support?
2.
An IBM i client partition has all disk resources virtualized. When the hosting IBM i partition is powered off or being restarted, users are unable to access the client partition. What changes can be made to ensure that the client system remains available without interruption?
3.
What are the three types of network adapters that can be assigned to an IBM i client partition?
4.
A customer has several client IBM i partitions hosted by a single VIO Server. The system has one Shared Ethernet Adapter. The administrator has noticed that network performance is significantly degrading as traffic increases. The system workload has not changed. Which statement describes a possible cause of this problem?
5.
An IBM i 7.1 partition hosts another IBM i 7.1 partition. The hosting partition provides disk and networking services for the client partition. An operator restarts the host partition from the HMC. What happens to the client partition?
6.
What boot mode is required when installing a hosted AIX or Linux partition?
7.
An administrator is setting up a Power 720 with VIO Server, using Integrated Virtualization Manager (IVM). IBM i will be in LPAR2. What is used to access the IBM i console during the initial setup of a client IBM i partition?
8.
A client partition has disk storage provided by two different hosting partitions. What method of disk protection on the client partition will help ensure that the client partition remains running in the event one of the hosting partitions becomes unavailable?
9.
A Power Systems server, running AIX, Linux and IBM i partitions, encounters performance problems. To investigate the problem, the administrator wants to collect high-level cross-partition performance data from an IBM i partition. What is required?
10.
A processor upgrade to a new 4-core Power 720 is planned, with processors capped and shared processor pools enabled, using the following configuration:
IBM i: Minimum - 1 .0; Desired - 2.5; Maximum - 2.5 Linux: Minimum - 0.5; Desired - 1.0; Maximum - 1.0
AIX: Minimum - 0.5; Desired - 0.5; Maximum - 1 .0
How many processor entitlements for IBM i are required on the new system?