If 10 Carpenters working 4hours a day can make 320 chairs in 200 days, then no. Of chairs made by 16 carpenters in 32 days each working 6hours in a day
X and Y can do a piece of work in 18 days and 14 days..X started the work alone, after 3 days Y joined till the completion of work. How long they did the work ?(approximately)
4 men and 6 women can complete the work in 8days. While 3 men and 7 women can complete the work in 10 days.In how many days 10 women will complete the work ?