1.
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time scheduling).
Which of the following properties for the resulting dependent requirements applies?
2.
Which of the following properties applies to multi-site planning in SAP ECC?
3.
Which of the following statements best defines SAP ERP?
4.
Which option for selecting a routing exists when you create a production order?

 
5.
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End:3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload:110%
- Number of individual capacities: 1
How large is the standard available capacity?
6.
An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB).
The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?
7.
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
8.
You want to create a new material that - is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directly
Which standard SAP material type do you use?
9.
In which master data object do you set the standard values for an operation?
10.
In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot).
What could be the reason?