Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
The availability check during production order creation should use a different scope of check than during order release.
How can you fulfill this requirement?
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.
How is the resulting firming interval specified in this scenario?