You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message.
What could be the reason?
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.
Which sequence category do you use to create the second sequence in the system?
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?