John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of
which are external to the organization. John needs to make certain that he communicates about risk in the most
appropriate method for the external stakeholders. Which project management plan will be the best guide for
John to communicate to the external stakeholders?
You are the project manager of the KJH Project and are working with your project team to plan the risk
responses. Consider that your project has a budget of $500,000 and is expected to last six months. Within the
KJH Project you have identified a risk event that has a probability of .70 and has a cost impact of $350,000.
When it comes to creating a risk response for this event what is the risk exposure of the event that must be
considered for the cost of the risk response?
John works as a project manager for ABD project. He and his team, are working on the following activities:
Relative ranking or priority list of project risks
Watchlists of low priority risk
Trends in Qualitative Risk Analysis results
On which of the following processes is John working on?
You are the project manager of the NHJ project for your company. This project has a budget at completion of
$1,650,000 and you are 60 percent complete. According to the project plan, however, the project should be 65
percent complete. In this project you have spent $995,000 to reach this point of completion. There is a risk that
this project may be late so you have taken some measures to recover the project schedule. Management would
like to know, based on current performance, what the estimate at completion for this project will be. What is the
estimate at completion?
Frank is the project manager of the NHQ project for his company. Frank is working with the project team, key
stakeholders, and several subject matter experts on risks dealing with the new materials in the project. Frank
wants to utilize a risk analysis method that will help the team to make decisions in the presence of the current
uncertainty surrounding the new materials. Which risk analysis approach can Frank use to create an approach
to make decisions in the presence of uncertainty?
You are a risk auditor for your company. You are reviewing the contract types a project manager has used in
her project. Of the following, which contract type has the most risk for the project manager as a buyer?
Jane is the project manager of the GBB project for her company. In the current project a vendor has offered the
project a ten percent discount based if they will order 100 units for the project. It is possible that the GBB
Project may need the 100 units, but the cost of the units is not a top priority for the project. Jane documents the
offer and tells the vendor that they will keep the offer in mind and continue with the project as planned. What
risk response has been given in this project?
You are the project manager of the GHE Project. You have identified the following risks with the characteristics
as shown in the following figure: How much capital should the project set aside for the risk contingency
reserve?