Frances is the project manager of a project in her organization. This project has a budget of $567,000 and is
schedule to last for three years. Frances wants to examine the risk events to determine which risk events have
the most potential impact on the project. Which modeling technique can help Frances to accomplish this goal?
You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk
register provides much information to you, the project manager and to the project team during the risk response
planning. All of the following are included in the risk register except for which item?
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the
qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis
process except for which one?
Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if
the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the
order. The NBG Company can guarantee orders within three days, but the costs of their products are
significantly more expensive than the current vendor. What type of a response strategy is this?
You are the project manager of the GHY Project for your company. You have completed the risk response
planning with your project team. You now need to update the WBS. Why would the project manager need to
update the WBS after the risk response planning process? Choose the best answer.
Adrian is a project manager for a new project using a technology that has recently been released and there's
relatively little information about the technology. Initial testing of the technology makes the use of it look
promising, but there's still uncertainty as to the longevity and reliability of the technology. Adrian wants to
consider the technology factors a risk for her project. Where should she document the risks associated with this
technology so she can track the risk status and responses?
Your project has several risks that may cause serious financial impact should they happen. You have studied
the risk events and made some potential risk responses for the risk events but management wants you to do
more. They'd like for you to create some type of a chart that identified the risk probability and impact with a
financial amount for each risk event. What is the likely outcome of creating this type of chart?
Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which
could cause the project to be late by more than a month. Marsha does not want this risk event to happen so
she devises extra project activities to ensure that the risk event will not happen. The extra steps, however, will
cost the project an additional $10,000. What type of risk response is this approach?
You are the project manager for your organization. You are preparing for the quantitative risk analysis. Mark, a
project team member, wants to know why you need to do quantitative risk analysis when you just completed
qualitative risk analysis. Which one of the following statements best defines what quantitative risk analysis is?