Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a
sizeable discount on all hardware if his order total for the project is more than $125,000. Right now, Eric is likely
to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he
cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric
consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware
for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric's
relationship with the vendor. What positive risk response has happened in this instance?
Della works as a project manager for Tech Perfect Inc. She is studying the documentation of planning of a
project. The documentation states that there are twenty-eight stakeholders with the project. What will be the
number of communication channels for the project?
You are the project manager for your organization. You are working with your project team to complete the
qualitative risk analysis process. The first tool and technique you are using requires that you assess the
probability and what other characteristic of each identified risk in the project?
You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process.
You are using organizational process assets to help you complete the quantitative risk analysis process. Which
one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative
risk analysis process?
Which of the following processes looks at the complex web of actors, rules, conventions, processes, and
mechanisms concerned with how relevant risk information is collected, analyzed and communicated, and how
management decisions are taken?
You are the project manager of the NNH project. In this project you have created a contingency response that
the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000
and is 45 percent complete - though the project should be 49 percent complete. The project has spent
$455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
You work as a project manager for BlueWell Inc. You are performing the quantitative risk analysis for your
project. One of the project risks has a 50 percent probability of happening, and it will cost the project $55,000 if
the risk happens. What will be the expected monetary value of this risk event?
Joyce is the project manager for her company. Joyce and her project team are working through the quantitative
analysis for certain risk events within her project. According to the enterprise environmental factors the project
manager is to perform sensitivity analysis on any risk with an impact greater than $5,000 in the project. What is
the sensitivity analysis?
You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with
your team. How many risk response types are available for a negative risk event in the project?
You are the project manager of the GHY project for your organization. You are working with your project team
to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you
will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification
process?