Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low
probability of happening, but the impact of the risk event could save the project and the organization with a
significant amount of capital. Ben assigns Laura to the risk event and instructs her to research the time, cost,
and method to improve the probability of the positive risk event. Ben then communicates the risk event and
response to management. What risk response has been used here?
Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree
Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat
even once it will delay the project's end date. You work with your project to create a response that should the
temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The
temperature of 430 is called what?
You are the project manager of the GHQ project for your company. You are working with your project team to
prepare for the qualitative risk analysis process. Mary, a project team member, does not understand why you
need to complete qualitative risks analysis. You explain to Mary that qualitative risks analysis helps you
determine which risks needs additional analysis. There are also some other benefits that qualitative risks
analysis can do for the project. Which one of the following is NOT an accomplishment of the qualitative risk
analysis process?
Sam is the project manager of a construction project in south Florida. This area of the United States is prone to
hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge
the possibility of hurricanes and the damage the hurricane could have on the project's deliverables, the
schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders
acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen. What
type of risk response is Sam using?
You are the project manager of a large project that will last four years. In this project, you would like to model
the risk based on its distribution, impact, and other factors. There are three modeling techniques that a project
manager can use to include both event-oriented and project-oriented analysis. Which modeling technique does
NOT provide event-oriented and project-oriented analysis for identified risks?
You are the project manager of the GHY project for your company. This project has a budget of $543,000 and
is expected to last 18 months. In this project, you have identified several risk events and created risk response
plans. In what project management process group will you implement risk response plans?
You are the project manager of QSL project for your organization. You are working with your project team and
several key stakeholders to create a diagram that shows how various elements of a system interrelate and the
mechanism of causation within the system. What diagramming technique are you using as a part of the risk
identification process?
Bill is the project manager for a project that will last six months and has a budget of $580,000. In this project a
high-risk has been identified with the new materials the project will be using. Bill would like to assign one
person, Beth, to be responsible to monitor this risk. Bill assigns Beth the authority to respond to the risk event if
it appears in the risk events that is likely to happen. In addition, Bill hires a consultant to work with Beth on this
area of the project. In this instance, who is the risk response owner?
Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to
express to her project team and to the management the importance of communication in this project. She
would like to show the number of stakeholder communication channels in the project. Based on this information
how many communication channels exist within this project?