A project has been ongoing for a year. Early in the year, its schedule performance index (SPI) was 1.2; its most recent SPI is 0.7.
What did the project manager use to track and communicate this information?
A project manager develops a risk breakdown structure (RBS) and divides it into four categories. Later, the team identifies a regulation issue with one of the
customer's requirements.
In what category should this new risk be included?
An external provider is late with the delivery of a finished item. As a measure of goodwill, and to maintain the project's schedule, the provider offers to bear the cost
of renting a temporary system.
Since no schedule slippage will occur, what should the project manager do next?
A project manager is creating a program evaluation and review technique (PERT) diagram. A primary activity on the critical path has a most optimistic time of three
weeks, a most pessimistic time of seven weeks, and a most likely time of five weeks.
What is the activity's expected time?
A project manager assumes a three-year, multiphase project with tight timelines. Stakeholder schedules permit time for addressing only essential activities
How should the project manager handle updating the lessons learned?