A work package has been scheduled to cost $1.000 to complete, and was to be finished today. As of today, the
actual expenditure is $1.200 and approximately half of the work has been completed.
Was is the cost variance?
As part of mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost.
You should calculate the forecast using which of the following methods?