Draw the precendence diagram for the dependencies and activity times below to answer the question. Use
AON or another technique to derive the answer using F-S relationships.
What is the critical path duration for the given schedule network?
Draw the precendence diagram for the dependencies and activity times below to answer the question. Use
AON or another technique to derive the answer using F-S relationships.
What is the total float on path BEG?