1.
Which of the following is a tool and technique to develop the schedule?
2.
Rolling wave planning is used as tool and technique in which of the following processes?
3.
Draw the precendence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships. What is the critical path duration for the given schedule network?
4.
Draw the precendence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships. What is the total float on path BEG?
5.
If the schedule Variance (SV) = $55, and the Planned Value (PV) = $11, What is the earned Value (EV)?
6.
What is the status of the project if the cost Performance index is 1.25 and the schedule Performance Index is 0.75?
7.
Which of the following will be required to perform simulation for schedule risk analysis?
8.
The risk register contains which of the following?
9.
Which of the following is an input to identify risk?
10.
Which analysis helps to determine the risks that have the most potential for impacting the project?