1.
Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?
2.
Project scope statement and resource calendars are inputs to what Project Time Management process?
3.
Which of the following tools or techniques is used for Estimate Activity Duration?
4.
Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
5.
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
6.
Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?
7.
Which technique is utilized in the Schedule Control process?
8.
Cost baseline is an output of which of the following processes?
9.
Analogous Cost Estimating relies on which of the following techniques?
10.
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: - Actual cost = $50,000 - Plan cost = $45,000 - Earned value = $40,000 What is the cost performance index?