1.
The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards is called __________.
2.
All of the following aid in achieving consensus EXCEPT __________.
3.
Which of the following statements is false?
4.
___________ is a groups of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
5.
Which of the following is not a process of project human resource management?
6.
To shorten project duration, resources have been added to tasks on the critical path. The plan should then be reviewed for the __________.
7.
The project manager's leadership style should be matched to the corresponding developmental level of the project team and should move through successive steps in the following order:
8.
The seller delivers a fixed price plus incentive fee project at a cost of $90,000. The terms of the contract are a ceiling price of $120,000, a target cost of $ 100,000, a target profit of $10,000, and a target price of $110,000.
The share ratio is 70/30. The final price (your total reimbursement) is _________.
9.
Estimate Costs_____________.
10.
A project management professional can compare earned value performance data to all of the following project management tools EXCEPT: