1.
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?
2.
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule variance (SV) for Task 8?
3.
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?
4.
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?
5.
One of the key benefits of the Plan Human Resource Management process is that it:
6.
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
7.
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
8.
A project's purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
9.
In the Define Activities process, the schedule management plan is used to:
10.
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a: