In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000.
If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
Directing another person to get from one to another using a known set of expected behaviors are the ability to lead a team and inspire them to do their jobs well is related to?
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?