Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs
to express to her project team and to the management the importance of communication in this project.
She would like to show the number of stakeholder communication channels in the project. Based on this
information how many communication channels exist within this project?
You are the project manager for your organization. You and the project team are developing the project
schedule for your current project. This project management process will create four outputs. Which of the
following is an output of the Develop Schedule process?
You are the project manager of the NDF project. You need to determine how often a complete project
report can be made, including forecasted project completion information for your project. How often should
the report be created?
You are the project manager of the OOI Project and you're forty percent complete with this project. The
project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive
scheduling you should be at the 45 percent milestone today, but due to some early delays you're running
late. What is the planned value of your project?
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a
BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be
at your second milestone, which accounts for half of the project completion. There have been some errors
in the project, which has caused you to spend $2,073,654. Based on the budget at completion, what is this
project's to-complete performance index?
You are working with your project team to control the project schedule. You will need five inputs to this
process throughout your project. Which one of the following is an output of the project schedule control,
and NOT an input?
You work as the project manager for BlueWell Inc. You are recording the activity status for your project
team's performance in the project. Based on the current performance your project is likely to be three
months late. What type of communication should be generated based on this performance issue?
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled
to last for three years. Your project is currently forty percent complete though it should be forty-five percent
complete. In order to reach this point of the project, you have spent $525,000. Management needs a
performance report regarding the NHQ project. What is the planned value for this project?
You are the project manager for the GRT Project in your organization. You have created your time duration
estimates based on historical information, but the estimates are not holding true in your current project.
Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team
for each of their activities. What is the formula used for PERT?