You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the
Define Activity process will help you in identifying the typical schedule milestones?
Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his
guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project.
The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?
Which of the group creativity techniques enhances brainstorming with a voting process used to rank the
most useful ideas for further brainstorming or prioritization?
Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is
scheduled to last for three years. His project is currently forty percent complete though it should be forty-
five percent complete. In order to reach this point of the project, he has spent $725,000. Management
needs a performance report regarding the NHQ project. Management is concerned that this project will be
over budget upon completion. Management would like to create a report telling them how much more the
project will need to complete. What value should Jack tell the management?
You are the project manager of the NHG. The following figure represents your project network diagram.
Management has asked that you add some features to the project scope. Through the change control
system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the
critical path, will decrease by three days. What affect does this have on the critical path?
Marty is the project manager of the recently completed NHK Project. The project was deemed successful
by the project customer and they have signed the formal acceptance documentation. Marty has written the
final project report, released the project team, and completed the lessons learned documentation. What
else should Marty do in the closure of the NHK Project?
Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project
planning processes is now coming into fruition. What individual should respond to the risk with the
preplanned risk response?
You are the project manager for your organization. You are working on creating the activity list so that you
can create the project schedule. This current project is similar to a project you have completed for your
company. You and the project team decide to use the previous project as a template for your current
project. A template can help you and the project team do all of the following except for which one?
You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and
organization impacted by the project. Mark, a project team member, has some doubts about the inputs of
the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in
project communication management?