You are the project manager of the NHQ project. This project is scheduled to last for six months and will
require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive
a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive
schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk
beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase
project risk?
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a
BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be
at your second milestone, which accounts for half of the project completion. There have been some errors
in the project, which has caused you to spend $2,073,654. What is this project's planned value?
You are the project manager for your organization. You want to record some details about the work that the
project team has to complete. You want to document the level of effort, where the work is to be performed,
and the person who will be responsible for completing the work. Which of the following is the best place to
document this information?
Steve is the project manager for the POK Project. He is working with the project customers to determine
how frequently they'd like to receive the project information. The customers would like weekly status
reports on how the project is performing. Where should Steve document this information?
Jenny is the project manager for her organization. Her project is not doing well on project schedule
performance, and management wants her to predict how the project schedule and cost will end.
Management has asked Jenny to report and forecast her project's performance based on the Judgmental
methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct
answer represents a complete solution. Choose all that apply.
You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The
activity list is based on the work packages defined in the project's WBS. Activities provide a basis for all of
the following information except for which one?
Tom is the project manager of the GHQ Project for his organization and he is working on recovering the
project schedule. As Tom examines his schedule, he is especially aware of project activities with hard
logic. What is hard logic?
You are the project manager for your organization. You are working with your project team to create the
schedule baseline for your project. You will also be creating the schedule data for this project. The
schedule data typically includes all of the following except for which one?
Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the
project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having
trouble completing his project assignment and will likely be at least two days late. Examine the figure given
below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end
date?