An activity has an Original Duration of 10, and a Remaining Duration of 10. The Actual Start is assigned to the
activity. Physical % is updated to equal 80%.
What is the Remaining Duration for this activity?
The Project Manager selects the "Update units when costs change on resource assignments" option on
Calculations tab in Project Details. The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource
on an activity. If the User assigns the activity an Actual Cost of $1,000, what is the Actual Units for the
resource?
You are a Portfolio Manager who opened a specific portfolio. You refreshed the filter. However, some of the
projects that were previously in the portfolio are no longer there. What happened?
You are a Portfolio Manager looking for a new portfolio that you manually created. You have clicked the Group
By drop-down list in Portfolios.
Which option should you select to quickly find your portfolio?
You are a Project Manager whose projects are integrated with Financial Management System (FMS). The FMS
pushes Actual Costs and Actual Hours to your projects as of the Actual Date. Updating Percent complete using
the pushed Actual Dates, Actual Costs, and Actual Hours has created inaccurate pictures of the overall %
complete, because there are steps within activities that clearly have not completed.
Which Percent Complete Type would be the best selection for activities in this project?