You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project
Server environment. The current environment consists of the following servers:
ABC-SQL1 runs Windows Server 2003 32-bit and Windows Server SQL Server 2000. ABC-SPS1 runs
Windows Server 2003 32-bit and Project Server 2003 with Service Pack 3. You have been instructed to
migrate the Project Server environment to Project Server 2010. What should you do to prepare the current
environment for the migration?
You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project
Server environment.
The current Project Server environment consists of the following servers:
ABC-SQL1 runs Windows Server 2008 64-bit and Windows Server SQL Server 2008. ABC-SPS1 runs
Windows Server 2008 64-bit and Project Server 2007. ABC.com users currently run Microsoft Office
Project 2007 on their Windows XP Professional client computers. Over the next two months, the client
computers will be migrated to Windows 7 and Microsoft Office Project 2010. You have been instructed to
configure a Project Server 2010 environment that will support both versions of Microsoft Office Project
during the migration. How should you configure the Project Server environment?
You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project
Server environment. The current Project Server environment consists of the following servers:
ABC-SQL1 runs Windows Server 2008 64-bit and Windows Server SQL Server 2008. ABC-SPS1 runs
Windows Server 2008 64-bit and Project Server 2007. You have been instructed to uABCrade Project
Server 2007 on ABC-SPS1 to Project Server 2010. Which of the following uABCrade methods would
ensure that all previous configurations of the farm are preserved?
You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project
Server environment. The current Project Server environment consists of the following servers:
ABC-SQL1 runs Windows Server 2008 64-bit and Windows Server SQL Server 2008. ABC-SPS1 runs
Windows Server 2008 64-bit and Project Server 2007. ABC.com client computers are currently being
uABCraded from Microsoft Office Project 2007 to Microsoft Office Project 2010.
You have been instructed to uABCrade the Project Server 2007 environment to Project Server 2010. After
the uABCrade, the Project Server 2010 environment should not allow connections from Microsoft Office
Project 2007. How should you configure the Project Server 2010 environment?
You work as a Project Manager at ABC.com. Your work includes managing projects using Project Server
2010 and configuring the Project Server 2010 environment. You have been tasked with configuring an
instance of Project Server 2010. You would like to customize the My Tasks page so that it displays 14 days
of future assignments without having to display all tasks. Which of the following actions should you take?
You work as a Project Manager at ABC.com. You are using the Project Server 2010 environment to
manage a large project. ABC.com has released a policy that states whenever a team member requests
time off, the project tasks should be rescheduled and timescales adjusted. To meet the requirements of the
policy, you have to be informed when members of the project team make use of their personal time sheets
to request time off. Which of the following actions should you take?
You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project
Server 2010 environment. The company has multiple projects in progress at any one time. ABC.com
employs several Project Managers to manage the projects using the Project Server 2010 environment.
Senior management at ABC.com uses the Project Server 2010 environment to gain an overview of the
progress of the current projects. You receive a complaint from senior management that the progress of
project tasks is displayed in different formats. You have been asked to configure the Project Server 2010
environment so that the progress of all project tasks is displayed as a percentage of work complete. How
should you configure the Project Server 2010 environment?
You work as a Project Manager at ABC.com. You are using the Project Server 2010 environment to
manage a complex project. You discover that you do not always receive timesheet updates submitted by
other members of the project team. You have been tasked with making sure that you always receive all
timesheet updates submitted by everyone in the project team. Which of the following actions should you
take?
You work as a Project Manager at ABC.com. You are managing a project using Project Server 2010. You
have been instructed to create a Project Server resource for the purpose of tracking the number of bricks
used in a new ABC.com housing development. Which of the following actions should you take?
You work as a Project Manager at ABC.com. You are managing a project using Project Server 2010. You
have been tasked with configuring a project resource so that the demand for the project is displayed by the
work estimates. You have also been informed that your configurations should not have an effect on the
availability of the resources. Which of the following actions should you take?