You work as a Microsoft Project Server 2007 administrator for TechWorld Inc. You need to configure
browser security settings for ActiveX controls in Project Web Access 2007. Which of the following actions
will you perform in order for the ActiveX controls to work properly?
You work as a Project Manager for company.com Inc. You need to call a meeting for a surprise party for a
project team member's birthday. Which of the following meeting templates would you use to accomplish the
task?
You are the Microsoft Project Server Administrator and you are working with Jane, a Project Manager in
your company. Jane has to create views for the resource managers and executives to analyze resource
availability and commitments. How will she accomplish the task?
You are the Microsoft Project Server administrator for your organization. The members of the management
committee has asked you to create a weekly report about the project's progress. They do not want to
connect to the Report Manager to view the report. What is most expedient method to create management's
report and deliver it to them on a weekly basis?
You are working with Henry to configure the Microsoft SQL Server Reporting Services for your standalone
server deployment. You and Henry have installed SharePoint and report server on a single server. Henry
wants to now configure an account to access the services with write and execute permissions. You
disagree with Henry that a new account is needed. What account is used for the service account?
You are the Microsoft Project Server administrator for your company. You have been working with your
project managers to develop a change control system for their projects. In the change control system, you
want to provide a method to document any changes from the areas of the project the change stems from.
There are, in practical project management, four areas of change control that should be managed by each
project manager. Which one of the following is not one of the four areas of change control?
Your project has a budget of $75,000 and is expected to last six months. Within your project, you are forty
percent complete and you have spent $35,000, and you want to compare the actual costs against the
earned value. What project component would you compare actual costs to in this instance?
You work as a Project Manager for Company Inc. You are using Microsoft Project Server and Project Web
Access to manage your projects. You need to work with your project team to create and identify
assignments for the current phase of your project. Within the project, there are several assignments that no
one in the project team is capable of completing because of time and resource limitations. You would like
to, for planning's sake, assign someone to the assignment and then replace the account with a contractor
later. What is the best approach for completing this task?
You are the Microsoft Project Server administrator for your project. Diane, a project manager, approaches
you about her project. She needs help in assigning tasks to resources. Her project has 59 project team
members, consisting of twenty general laborers, ten framers, ten electricians, five plumbers, five
carpenters, five general contractors, and four tile workers. She wants to create a way to assign a task to
these groups of resources rather than individuals within these groups of workers. For example, she has a
task in the project to "run CAT6 cable" that any electrician could complete. How can she solve this
problem?