You are responsible for managing ten resources who work on multiple projects that are published to Microsoft
Office Project Server 2007. Your organization requires that resources spend no more than 20 percent of their
time on administrative tasks. You need to monitor resource time for the requirement that non-project time must
not exceed 20 percent. What should you do?
You are the project manager for a consulting company that is deploying Microsoft Office Project Server 2007.
Your administrator has set up the ability to track non-billable time in the timesheet system; however, this line
does not appear in your timesheet. In Microsoft Office Project Web Access, you need to configure your
timesheet to track non-billable time for all your tasks in the timesheet. What should you do?
You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project
Server 2007. You need to record the hours you work on assigned tasks. What should you do?
You are a resource manager. One of the resources assigned to a project that is published to Microsoft Office
Project Server 2007 has submitted a timesheet with incorrect actual hours for a project activity. You need to
ensure that the number of hours is corrected and that a historical record of this transaction is logged. What
should you do?
You are developing a project plan that is saved to Microsoft Office Project Server 2007. The project was
created with generic resources assigned to tasks. In Microsoft Office Project Web Access, you need to
substitute named resources for the generic resources in the plan. What should you do?
Your organization tracks deliverables in Microsoft Office Project Server 2007. You need to create a report listing
the total number of deliverables in the entire project portfolio.
What should you do?
In Microsoft Office Project Professional 2007, you have a project plan that has a task linked to a deliverable in
another project. The Gantt chart shows that the other project deliverable finish date is a week in the future. You
need to move your task to match the deliverable finish date. What should you do?
In a project that is published to Microsoft Office Project Server 2007, your resources submit their progress
updates to you for approval. You are leaving on vacation for 2 weeks.
You need to ensure that another project manager can approve resource task updates while you are gone.
What should you do?
You are tracking a set of projects that are saved to Microsoft Office Project Server 2007. Your organization's
directors have requested a weekly report displaying the progress of all active projects. They want to see cost
and work grouped by a custom field for product. They cannot log on to Microsoft Office Project Web Access. In
Project Web Access, you need to supply this report. What should you do?
You manage a set of projects that are saved to Microsoft Office Project Server 2007. You have been asked to
generate a report for each project that displays the work performed by day and that can be filtered based on a
customer custom field. In Microsoft Office Project Web Access, you need to create this view. What should you
do?