You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project
Server 2007. You need to record the hours you work on assigned tasks. What should you do?
In a project that is published to Microsoft Office Project Server 2007, your resources submit their progress
updates to you for approval. You are leaving on vacation for 2 weeks.
You need to ensure that another project manager can approve resource task updates while you are gone.
What should you do?
As a service manager, you are responsible for service requests. Working in Microsoft Office Project Web
Access, you need to set up a process so that available service personnel can assign themselves to the next
unassigned request. First, you create an activity plan. What should you do next?
A project that is saved to Microsoft Office Project Server 2007 currently contains generic resources. The next
step is to replace the generic resources with named resources who are available to work on your project. From
the Build Team from Enterprise screen in Microsoft Office Project Professional 2007, you need to request a
named resource from the enterprise resource pool for each generic resource. What should you do?
You are developing a project plan that is saved to Microsoft Office Project Server 2007. The project was
created with generic resources assigned to tasks. In Microsoft Office Project Web Access, you need to
substitute named resources for the generic resources in the plan. What should you do?
Your organization uses Microsoft Office Project Server 2007. A number of task enterprise custom fields have
been defined. You need to ensure that all project managers use a custom view that includes these fields when
they develop their project plans. What should you do?
You are the manager of a project that is published to Microsoft Office Project Server 2007. You want to work on
the project, but Microsoft Office Project Professional 2007 is not installed on the computer you are using. You
need to use Microsoft Office Project Web Access to add a new resource to your project plan. What should you
do?
You are the manager of a project that is published to Microsoft Office Project Server 2007. You do not know
when team members add documents to the Deliverables library of the project workspace site. You need to
configure Microsoft Office Project Web Access so that you receive automatic notifications whenever new
documents are added to the library. What should you do?
In your organization, Gantt Chart views on the Project Details page do not show deadlines. You manage a
project with multiple deadlines that is saved to Microsoft Office Project Server 2007. You need to display a
Gantt chart with project deadlines without changing any of the views used by other people. What should you
do?
An error has been discovered related to a time estimate in a template that is saved to Microsoft Office Project
Server 2007. Working in Microsoft Office Project Professional 2007, you need to update the existing template
without duplicating the template file. What should you do?