1.
Resources have submitted time worked for a project that is published to Microsoft Office Project Server 2007, and you have accepted their updates into the plan. However, when you view a report on the Data Analysis page of Microsoft Office Project Web Access, you notice that the updates are not in the report. You need to generate a report now that contains the latest information. What should you do?
2.
In a project that is published to Microsoft Office Project Server 2007, your resources enter actual work and remaining work for their tasks and submit the updates to you. You need to see the impact of these updates in Microsoft Office Project Web Access before accepting them. What should you do?
3.
You create and save a project schedule in Microsoft Office Project Professional 2007. You need to add some deliverables to your project tasks. However, the Manage Deliverables feature is not available. What should you do?
4.
In Microsoft Office Project Web Access, you want to analyze the work performed on your projects over the last 2 years. You need to extract tabular information grouped by year, month, team, and resource. What should you do?
5.
In a project that is published to Microsoft Office Project Server 2007, some tasks are dependent on an external task. In Microsoft Office Project Web Access, you want to inform the relevant resources that they can begin their tasks. You need to use a status report to record completion of the external task. What should you do?
6.
You manage a project that is published to Microsoft Office Project Server 2007. A resource has quit his job, and a replacement has been hired. In Microsoft Office Project Professional 2007, you need to replace the old resource on all of his remaining scheduled work with the new resource. What should you do?
7.
You manage a portfolio of projects that are saved to Microsoft Office Project Server 2007. You are asked to provide detailed information about individual resource utilization on all tasks in all of your projects. Using Microsoft Office Project Web Access, you need to examine all scheduled work for all project resources. What should you do?
8.
You hire a new resource for project work. All resources must be authenticated to Microsoft Office Project Server 2007 using Windows Authentication. You need to assign tasks to this new resource, before the resource has a Windows account. What should you ask the administrator of Project Server to do?
9.
You manage a project that is saved to Microsoft Office Project Server 2007. One of the resources working on the project is an external contractor. His cost to the project is a fixed price per hour of work performed. To add this resource to the enterprise resource pool, you fill out a new resource form on the Resource Center page in Microsoft Office Project Web Access. You need to track the cost of this resource to the project as he completes work and submits his timesheets. What should you do?
10.
In a project that is published to Microsoft Office Project Server 2007, resources reassign tasks to other resources as necessary. You need to identify tasks that have been reassigned. What should you do?