You are preparing to update the status of a baselined project plan in Microsoft Office Project Standard 2007.
You need to compare the Gantt chart before and after the update within the same project plan. What should
you do?
In Microsoft Office Project Standard 2007, you are tracking a project by duration. The Updating task status
updates resource status option is not activated. You need to display the current status of the project. What
should you display?
A project that you are tracking in Microsoft Office Project Standard 2007 has tight deadlines that must be met.
For some tasks, a delay of more than 5 days will impact the project end date. You need to identify these tasks
as critical. What should you do?
You are creating a project schedule in Microsoft Office Project Standard 2007. For a previous project, you
created a project calendar that includes public holidays. You need to add the custom project calendar to your
current project. What should you do?
You are creating a project plan in Microsoft Office Project Standard 2007. Your organization does not allow
resources to work overtime. Every time you make a change to your schedule, you need to ensure that
resources are not over-allocated, by using the method that gives you the most control.
What should you do?
The project schedules you manage in Microsoft Office Project Standard 2007 all follow standard project
lifecycle phases. You need to be able to display all tasks of all projects by phase. What should you do?
You are managing a project in Microsoft Office Project Standard 2007. The project follows the plan shown
below: Task 1 is 100 percent complete. Tasks 2 and 4 are each 50 percent complete. The forecast duration of
Task 2 is half a week more than its baseline duration. Task 3 cannot start until Task 2 is complete. Task 4 is 1
week late. You need to modify the schedule to meet the original finish date. What should you do?
You are creating a schedule in Microsoft Office Project Professional 2007. For budgeting purposes, you
allocate resources 6 months in advance of the project. You do not know who will be assigned to your project at
this time. You need to forecast when the project will need resources with specific skills. What should you do?
You are creating a project schedule in Microsoft Office Project Standard 2007. For a previous project, you
created a project calendar that includes public holidays. You need to add the custom project calendar to your
current project. What should you do?
In Microsoft Office Project Standard 2007, you are changing the durations of several tasks in a project
schedule. You need to immediately display the effect of your changes on the start and finish dates of other
tasks. What should you do?