Assuming, option to Cost Labor on Entry radio button is selected, and when using the Timecard or Timesheet with Rate/Amount Entry screens, rates and labor cost amounts are displayed when the following entry type is used?
Week Maintenance is set up so that the week ending May 31 posts to Labor and Fiscal Period 05-2002. Period 05-2002 is closed in the Project Controller module, and the current period represents fiscal period 07-2002. There is still a timecard in process for the week ending May 31, 2002. If the timecard is posted now, what will occur?
A salaried non-exempt employee works 50 hours in a week, 40 hours are regular hours and 10 hours are overtime. This employee's salary is $1,000 per week and $25 per hour. Assuming the employee worked on the same project all week, what is the cost to the project?