1.
You need to meet Holly Holts reporting requirement. What should you do?
2.
You need to meet Andrea Lee's requirements for earned value charts. What should you do?
3.
You need to address the need for an enterprise framework for varying project types. What should you do?
4.
Page 19 of 43 Exam Name: PRO: Microsoft Office Project Server 2007, Managing Projects and Programs Exam Type: Microsoft Case Studies: 12 Exam Code: 70-634 Total Questions: 82 In order to comply with the new government rules, you need to create a system that requires resources to account for all hours worked, by project. How should you have resources enter their time?
5.
You need to support the variance monitoring requirements of the project managers. What should you do first?
6.
You have just completed a project. You need to meet management's requirement for historical reporting. What should you do?
7.
You need to meet management's requirement for estimated cost to completion reporting. What should you do?
8.
You need to forecast resource requirements for a task. What should you do?
9.
One of Trey Research's critical tasks is delayed. You need to bring the task back on track by using new contractors. What should you do?
10.
You need to support Rob Young's preview requirements. Where should you preview the task updates?