One of your company's workcenter is going to be used for two hours in each eight-hours shift for training.Your company uses operation scheduling. What adjustment must you make for this work center so only six hours of production work are planned for this work center shift?
All items in inventory have a batch number. The batch number is not being printed in the production picking list journal. What can be done to ensure the batch number prints on the report?
You are using MD_AX 2009 Master Planning to generate planned orders for raw materials. The raw material items currently use the site and warehouse storage dimensions. How can you configure MD_AX 2009 to generate an individual requirement for each storage location?
A company manufactures televisions for customers on demand, but does not keep cabinets and prints in inventory. Therefore the production of cabinets and prints is carried out paralell to assembly of the televisions. What is the correct solution to use in this situation?