You are the consultant on a Microsoft Dynamics NAV 2009 implementation. Your client is setting up Item
Cards. In the Flushing Method field, the available options are Manual, Forward, and Backward. Your client
asks you to explain how material is consumed when forward flushing is selected and routing link codes are
not used. What explanation do you provide to your client?
You are a consultant implementing Microsoft Dynamics NAV 2009. You are assisting your client in setting
up a Work Center. On the Scheduling FastTab your client has selected minutes in the Unit of Measure
Code field.
Your client tells you that for the Assembly Department, there are five employees working an eight hour shift.
Your client also tells you that time study results indicate that the employees work on average 6.4 hours of
the eight hour shift.
What entries do you advise your client to make in the Capacity and Efficiency fields on the Scheduling
FastTab?
You are a technical support specialist for Microsoft Dynamics NAV 2009. You receive a call from a client
requesting assistance with production BOMs. Your client has an existing BOM for a finished good. For a set
period of time, your client wants to include an additional component when producing the finished good.
What advice do you give your client to handle the additional component for the finished good?
You are a consultant implementing Microsoft Dynamics NAV 2009. You guided your client through the steps
to populate a Planning Worksheet using the MPS selection for the Calculate Net Change Plan function.
One of the lines populated in the worksheet has the MPS Order check box selected. Your client needs to
generate the dependent requirements for the line. What function do you have your client perform next so
that planning is complete for the line?
The overall purpose of MRP is to provide timephased formal plans, by item, to supply the right item at the
right time, in the right place, and in the right quantity. MRP uses action messages to tell the user what must
be done to meet demand. What action messages are displayed in the planning worksheet? Choose the 3
that apply.
You are a technical support specialist for Microsoft Dynamics NAV 2009. The production planner for one of
your clients contacts you regarding a planning problem with a particular finished good. The planner explains
that for a recently modified production BOM, the planning results are incorrect.
You determine that the production BOM for the finished good was recently modified to include an additional
level; afterwards, the status was updated to certified. You also confirm with the client that the Dynamic Low
Level Code check box is not selected in Manufacturing Setup. Based on your conversation, what is the first
step you have the planner perform to properly plan the finished good?