1.
You are a technical support specialist for Microsoft Dynamics NAV 2009. The production planner for one of your clients contacts you regarding a planning problem with a particular finished good. The planner explains that for a recently modified production BOM, the planning results are incorrect. You determine that the production BOM for the finished good was recently modified to include an additional level; afterwards, the status was updated to certified. You also confirm with the client that the Dynamic Low Level Code check box is not selected in Manufacturing Setup. Based on your conversation, what is the first step you have the planner perform to properly plan the finished good?
2.
What is the purpose of the Matrix per Version window?
3.
What status codes are available for production orders?