When a production order is released, certain conditions must be met for all of the components to be
automatically consumed from inventory. What conditions must be met? Choose the 3 that apply.
You are the consultant on a Microsoft Dynamics NAV 2009 implementation. You are reviewing
Manufacturing Setup, explaining the purpose of the various fields to your client. What explanation do you
provide for the use of the Dampener (Time) and Dampener (% of Lot Size) fields?
You are a technical support specialist for Microsoft Dynamics NAV 2009. One of your clients contacts you
for assistance in setting up a subcontractor where the rate charged is different for each process. Your client
is unsure of the necessary setup and asks for your guidance. What steps do you have your client complete
to set up the subcontractor? Choose the 2 that apply.
After a production order is manually created, how can a production planner determine whether the
component items are available? Choose the 2 that apply.
To use putaway features, a production manager must first create an inbound warehouse request for a
released production order. How can an inbound warehouse request be created? Choose the 2 that apply.
You are a consultant implementing Microsoft Dynamics NAV 2009. You are explaining the concept of
netting to your client's production planner. For this discussion, you and the planner have agreed to assume
a production forecast of 500 bikes for a particular month. You then introduce two scenarios for sales orders
for the bikes in that month. For the first scenario, orders are received for 400 bikes. For the second
scenario, orders are received for 650 bikes. Based on the sales orders, the planner wants to know the
impact the production forecast has on gross requirements. Considering sales orders, how does the
production forecast affect gross requirements for each scenario?
You are a technical support specialist for Microsoft Dynamics NAV 2009. Your client's production planner
requests assistance with production forecasts. The planner has entered a sales forecast for 500 bikes in
April. Lamps are a component in the BOM for bikes (one lamp per bike) and are also sold directly to
customers.
For bike lamps in April, the dependent demand is 500 units and the independent demand is 20 units. The
production planner wants to know the correct entry to make in April for the sales forecast for bike lamps.
What entry do you tell the production planner to make in the sales forecast?