1.
You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?
2.
Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?
3.
You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?
4.
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
5.
You need to compare the total work of your project's deliverables against the baseline work. What should you do?
6.
You need to create a project plan that accommodates the corporate holiday calendar. What should you do?
7.
You need to create a project plan in Project 2010 from a list of tasks in a Microsoft Access 2010 database. What should you do?
8.
You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
9.
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
10.
The red person icon is displayed next to one of your tasks. You need to find out the reason for the display of the icon. What should you do?