You set up three pay-when-paid (PWP) terms and assign them to the vendors for a project. For the first
PWP term,you set the account code for all vendors (All). For the second PWP term,you set the account
code for an individual vendor (Table). For the third PWP term,you set the account code for a group of
vendors (Group).
What is the order of precedence for assigning the PWP terms when you create a project purchase order?
You set up a new fixed-price project and manually create a work breakdown structure (WBS) in the new
project.
What happens to the existing WBS when you copy activities to the new project from a WBS template?
You have a project with multiple funding sources.
You need to set up the allocation of funds in the project contract.
How many funding sources can you select for rounding off the differences?
You create a project purchase order with both pay-when-paid (PWP) and customer retention terms
enabled. The PWP threshold percentage is defined as 70% for the vendor. The customer retention
term,each time the customer is invoiced,is 25% of the invoice amount. You invoice the customer for 90,000
USD. What is the minimum amount that you need to receive from the customer so that you can pay the
vendor?