You are using Microsoft Project.
Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see
this information in a simple layout that does not include task details.
You need to show one line item that displays all the requested information in the Gantt view.
What should you do?
You use Microsoft Project to create a new project from a corporate template.
You observe that the information displayed for each task in a phase named Consumer Testing is shown with horizontal lines through the text, and the text is lighter
as compared to other tasks in the schedule.
You need to ensure that the Consumer Testing phase is available for this schedule.
What should you do?
This question requires that you evaluate the underlined text to determine if it is correct.
You are a project manager on a book publishing project. You have a task named Bind the pages. You have a resource that is available full-time for the project, but
will only work on this task half-time to remain available for other tasks on the project at the same time. You will assign the resource to the task at 50 percent units to
ensure the task and the resource are scheduled correctly.
Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the
statement correct.
You are managing a project by using Microsoft Project. The project has a baseline that was set after the schedule was approved. The project has a work budget.
The project is currently 50 percent complete. You are using a standard report, with no customization.
You need to create a report that graphically compares baseline with actual work completed.
Which two actions will achieve the goal? Each correct answer presents a complete solution?
This question requires that you evaluate the underlined text to determine if it is correct.
You assign a resource to a Fixed Duration task, but that resource is unavailable for the timeframe in which the task needs to occur. You need to assure that the
task is not delayed. Change the task calendar to 24 hours.
Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the
statement correct.