An IS auditor finds that a system under development has 12 linked modules and each item of data can carry up to 10 definable attribute fields. The system handles several million transactions a year. Which of these techniques could an IS auditor use to estimate the size of the development effort?
When identifying an earlier project completion time, which is to be obtained by paying a premium for early completion, the activities that should be selected are those:
An IS auditor invited to a development project meeting notes that no project risks have been documented. When the IS auditor raises this issue, the project manager responds that it is too early to identify risks and that, if risks do start impacting the project, a risk manager will be hired. The appropriate response of the IS auditor would be to: