You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in
the Sprint. Who should you invite as a required attendee to the Sprint Review?
1. Product Owner(s)
2. Development Team
3. Business Users
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all
tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog
item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three
tasks?