For her injection molding project a Belt needed to track the percentage of defectives of a particular sample set so she used a ___________ to display the data?
If the production is for higher volume and monitoring and the Mean and variability is to be monitored for four machines producing product and the characteristic to
be monitored is Variable Data, which SPC Chart is best to be selected?
When a Belt Poka-Yoke's a defect out of the process entirely then she should track the activity with a robust SPC system on the characteristic of interest in the
defect as an early warning system.
Following the completion of a LSS project the Belt not only creates a Control Plan he also develops a _____________ so those involved in the process know what
to do when the critical metrics move out of spec.