1.
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
2.
The project management processes presented in the PMBOK Guide
3.
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
4.
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
5.
What is the definition of Direct and Manage Project Execution?
6.
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
7.
Which of the following techniques is used during Control Scope?
8.
Which type of chart is a graphic representation of a process showing the relationships among process steps?
9.
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
10.
Which tool and technique is used in Conduct Procurements?