1.
Without a Risk Register how can project risks, the progress of risk actions taken to date and the current status of residual risks be measured?
2.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. Which statement applies to the Introduction section?
3.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. Which statement applies to the Communication procedure section?
4.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. Which statement applies to the Tools and techniques section?
5.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. What statement applies to the Records section?
6.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. Which statement applies to the Timing of communication activities section?
7.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. Which statement applies to the Stakeholder analysis: Interested parties section?
8.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information. Which statement applies to the Information needs for each interested party section?
9.
Who is responsible for appointing the Project Manager?
10.
Who is responsible for the initial creation of the Configuration Item records?