Which of the following statements are True:
1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization.
2. Quality planning is about defining products required of the project with their respective quality criteria, methods and responsibilities.
3. Quality control focuses on the operational techniques and activities used to carry out quality inspections
4. Quality assurance ensures that quality methods are being correctly followed.
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the
following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their
everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff
schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the
following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their
everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff
schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the
following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their
everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff
schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the
following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their
everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff
schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the
following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their
everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff
schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the