1.
Which does NOT reflect the PRINCE2 principle of continued business justification?
2.
Which characteristic distinguishes a project from regular business operations?
3.
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
4.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
5.
Which role is responsible for creating Checkpoint Reports?
6.
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
7.
Which is a true statement about time-driven controls?
8.
How many management stages should a PRINCE2 project consist of?
9.
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
10.
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?