1.
When considering risks, which describes an opportunity in a project?
2.
Which of the following statements about lines of authority and reporting are true?
1, The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
3.
Which may be funded from a risk budget?
4.
What is the first task of product-based planning?
5.
How many tasks does the product-based planning technique describe?
6.
Which is an objective of the quality review technique?
7.
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
8.
If an informal issue is defined as a problem or concern, where should it first be recorded?
9.
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,
10.
Which is the purpose of the Change theme?