1.
To add value to the business, what are the four reasons to monitor and measure?
2.
Before embarking on the 7-step Continual Service Improvement (CSI) process, which of the following items need to be identified?
3.
What is the definition of an Alert?
4.
Which of the following would NOT be a task carried out by the Request Fulfillment process?
5.
Which of the following CANNOT be stored and managed by a tool?
6.
Which process would you MOST expect to be involved in the management of Underpinning Contracts?
7.
What is the name given to the individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks?
8.
The difference between service metrics and technology metrics is BEST described as?
9.
Which of the following describes risk proximity?
10.
Which of the following is the BEST definition of an Incident?