1.
A Project Manager wants to track not just the rate of progress against tasks, but also the overall morale and happiness of the Scrum team. What device will help track morale and happiness?
2.
When is a Sprint complete?
3.
What is an information radiator?
4.
A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint. What is the most likely reason that the team did not meet the Sprint objectives?
5.
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time. What would be the elapsed time required to complete the Story?
6.
Who knows most about the progress towards a business objective or a release?
7.
What is the best way to split up teams on a large project which is implemented using Scrum?
8.
Collaboration is the most important parameter for the success of an Agile team. What term best describes this type of interaction?
9.
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story?
10.
A team has eleven members spread over two locations across two time zones. One of the locations has six team members and the other team has five. Where should a Scrum Master be located?