A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint. Who may best prepare this report?
During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13. What is the velocity of the team?
Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan. What term best describes the multi-level planning?