1.
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint. Who may best prepare this report?
2.
Who should update the work estimates during the Sprint?
3.
Which means of communication is the most preferable to clarify the interpretation of a requirement?
4.
In a Scrum project, when would a requirement get added to the Product backlog?
5.
What is the objective of the Scrum-of-Scrums meeting?
6.
During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13. What is the velocity of the team?
7.
Which statement describes Release Planning?
8.
Agile planning happens at multiple levels including a daily plan,a sprint plan and a strategic plan. What term best describes the multi-level planning?
9.
During the release planning meeting, it is difficult to agree on priorities. Sales want to implement some new features to catch up with the competitors. Marketing want to work on a mobile interface that can prove to be a competitive differentiator. Customer support want better logging and auditing capabilities to improve maintainability. What should be done to set the priorities?
10.
How should 'done' be defined when multiple teams are working on a single product?