1.
For completion of a project, the critical path of the network represents
2.
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
3.
Which of the following excavators is most suitable for digging under water?
4.
Rolling resistance of a wheel depends upon
(i) Vehicle load
(ii) Grade
(iii) Ground conditions
5.
Residential buildings are treated as
6.
Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
7.
The critical activity has
8.
The object of technical planning, is
9.
Total float for any activity is defined as the difference between
10.
Interfering float is the difference between