1.
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he
2.
Free float is mainly used to
3.
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
4.
Preliminary project report for a road project must contain
5.
Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is
6.
The salient feature of functional organization is
7.
The time corresponding to minimum total project cost is
8.
The process of incorporating changes and rescheduling or replanning is called
9.
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
10.
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as